5 weeks from possession to trading.
Works Undertaken
- Ceilings had to be reinforced and walls lined
- New staff area and changing rooms formed including MF ceilings and stud partition walls
- Decoration internally and externally
- Floors latex prior to installation of Polysafe Arena tiles being installed throughout
- Display equipment installed
- New fire rated doors and skiting installed
- Plumbing was upgraded to allow installation of new DDA equipment
- HVAC system installed
- Intruder Alarm and Signage
- Electric distribution board upgrade to current standards for lighting, display equipment and general power
- Signage