This was our first full new site location for SIXT.  The project was carried out over a 4-week program

Work Undertaken

  • Trades on site included
    • Electricians
    • HVAC
    • Plumbing
    • Flooring
    • Signage
    • Ground workers
  • New shopfront
  • Ground works for the drainage system to the car wash bays
  • Form new stud partition offices and glass partition offices
  • Installation of bespoke joinery
  • Groundworks to form foundation of new totem pole signage and pad foundations for the wash bay structure
  • Electrical works both inside and outside including high level lighting and illuminated signage
  • Finishes included vinyl flooring, decorations, and new staff kitchen